On site

Daily reports

A daily progress report from site - manpower, work done, hindrances and photos.

Where: Project sidebar → Daily reports

Who: Filing a report needs the "submit daily reports" permission.

File today's report

  1. 1Open Daily reports and pick today.
  2. 2Check the report details - site, client, contractor and working hours carry over from the last report - then the weather and a summary of the day.
  3. 3Manpower - each agency or contractor, their trade, and skilled and unskilled head count.
  4. 4Work done - each activity, where, and the planned and achieved quantity, plus an optional Details box for anything the rows don't cover.
  5. 5Materials received and equipment - deliveries with supplier and challan, and machines with hours worked and idle.
  6. 6Hindrances / delays - anything that held work up: its cause, where, from and to, and the hours lost.
  7. 7Add safety, the plan for tomorrow, any instructions or visitors, and site photos.
  8. 8Click Save draft to finish later, or Submit report when it's done.
  • Filled it on paper or in Excel? Click Excel template for the same format, then Fill from Excel to upload a filled copy - the report fills itself, ready to check and submit.
  • Tick Add to stock on a delivery (with inventory on) and it goes into Materials → Goods received when the report is submitted. Got the quantity wrong? Reopen, fix it and submit again - the same entry, and the stock, are corrected.
  • Share a submitted report as a PDF or straight to WhatsApp.
  • The list shows which days are Submitted, Draft or Missing.
  • An end-of-day reminder nudges everyone who can file reports if today's isn't in. Set its time, and whether to skip Sundays, on the Daily reports page.
  • The Hindrance register collects every delay from every report, by cause and hours lost. Download it as Excel or PDF in the same format as the free hindrance register template: a delay logged on consecutive days is one entry from its date of occurrence to its date of removal, counted in days, with overlapping days counted once. Add the Agreement no., Date of start and Stipulated completion once on the register page, and they print at the top.
💡Write hindrances down every day. A daily record of causes is what backs up a time-extension claim later.