Daily progress report (DPR) format for construction - free Excel download

A ready-to-use daily progress report format for site engineers: manpower, work done, materials received, equipment, hindrances, safety and tomorrow's plan on one A4 page. Download it free, print it, or fill it in on a computer.

Free for up to 10 users No credit card Works on any phone
raidzo-dpr-format.xlsx

Daily progress report

Free download

9

Sections

2

Sheets

A4

Page

  • 2. Manpower on site42
  • 3. Work done today4 items
  • 6. Hindrances / delays3 h

Opens in Excel, Google Sheets and WPS Office

DPR format downloaded
01

Download the DPR format

The workbook has two sheets: a blank format to print or fill in, and a filled example of a day on site, so a new site engineer can see what a good report looks like. Manpower and hours lost add up by themselves.

It's free - no sign-up and no email needed. Add your company name and logo, and change the columns to suit your site.

02

What's in the format, section by section

SectionWhat to writeExample
HeaderProject, site, client, contractor, report no., date, weather, temperature, working hours and who prepared itDPR-142 · 7 Oct 2026 · Clear, 32°C
1. Summary of the dayTwo or three lines on how the day wentSlab shuttering on 3rd floor completed
2. ManpowerEach agency or contractor, their trade, and skilled and unskilled head countSharma Constructions · Masons · 12 + 8
3. Work doneActivity, location, planned and achieved quantity and unit - plus a details box for anything the rows don't coverBrickwork, 2nd floor east wing · 24 planned, 18 done (m²)
4. Materials receivedMaterial, quantity, supplier and challan or invoice numberCement OPC 53 grade · 200 bags · CH-8812
5. EquipmentEach machine, hours worked, idle hours and why it was idleConcrete mixer · 6 h worked · 2 h idle
6. HindrancesCause, details, location, time and hours lostCement delivery late - 3 hours lost
7. SafetyIncidents, near misses and toolbox talksToolbox talk on working at height
8. Plan for tomorrowThe work planned for the next dayRebar for 3rd floor slab (2.5 t)
9. Remarks and signaturesInstructions and visitors; signed by the site engineer, project manager and clientClient visit at 4 pm
03

How to fill a daily progress report well

  1. 1Fill it the same day, before you leave site - not from memory at the end of the week.
  2. 2Write quantities with units (18 m², 1.5 t), not just "brickwork in progress". Planned against achieved shows straight away when the site is falling behind.
  3. 3Count manpower by agency and trade from the attendance, not from what the contractor tells you.
  4. 4Write down every hindrance, even a two-hour one, with its cause. Small delays add up, and they're your evidence in an extension of time claim.
  5. 5Note the challan number of every delivery, so the report can be matched with the supplier's bill.
  6. 6Get it checked and signed by the project manager or the client's engineer, and keep every report - together they're the project's diary.
04

When paper and Excel start to hurt

A spreadsheet DPR works for one site. With several sites, reports arrive late, by email or WhatsApp, in slightly different versions of the format - and when you need every hindrance from the last three months, someone has to open ninety files.

In Raidzo, the daily report has the same sections as this Excel format. The site engineer fills it from their phone in a few minutes, with photos - or uploads a filled copy of this sheet and the report fills itself. You're notified the moment it's submitted, missing days are flagged, the report can be shared as a PDF or on WhatsApp, and every hindrance lands in a hindrance register by itself. Free for up to 10 users.

FAQ

Frequently asked questions

What is the format of a daily progress report in construction?

A header with the project, date, weather and report number, followed by a summary of the day, manpower by agency and trade, work done with quantities, materials received, equipment, hindrances with hours lost, safety, the plan for tomorrow and signatures. The free Excel format on this page has all of these on one A4 page.

Is this DPR format free?

Yes. Download the Excel file without signing up, and change it however you like.

Can I use the DPR format in Google Sheets?

Yes. Upload the .xlsx file to Google Drive and open it with Google Sheets - the totals keep working. It also opens in WPS Office and LibreOffice.

Can I print it?

Yes. The sheets are set up for A4 and fit the page width, so you can print the blank format for site engineers who prefer pen and paper.

Who prepares the DPR on a construction site?

Usually the site engineer or supervisor, at the end of each working day. The project manager checks it, and it's often shared with the client or consultant.

Is there an app instead of an Excel DPR?

Yes - Raidzo is a daily progress report app that's free for up to 10 users. Site engineers fill the report on their phone with photos, and you're notified when it's submitted.

Try it on your next project