Free hindrance register format

Hindrance register format - free Excel download

A hindrance register for construction contracts, with the columns an engineer-in-charge expects: nature of hindrance, dates of occurrence and removal, period, overlapping period and net delay. The day counts and totals work themselves out.

Free for up to 10 users No credit card Works on any phone
raidzo-hindrance-register-format.xlsx

Tower B · Sep - Oct

Free download

4

Hindrances

19 d

Net delay

2 d

Overlap

  • Drawing / design pending7 days
  • Weather (overlapping)0 days
  • Client decision / change12 days

Period and net delay worked out for you

Hindrance register downloaded
01

Download the hindrance register format

Two sheets: a blank register with 30 numbered rows, and a filled example that shows how overlapping hindrances are handled. Pick the cause from a drop-down, enter the two dates, and the period and net delay fill in by themselves.

Free - no sign-up and no email needed.

02

The columns in the register

ColumnWhat to writeExample
Nature of hindranceThe cause, picked from a listDrawing / design pending
DetailsWhat happened, and what work stoppedRevised slab drawing for 4th floor not received
Work affected and locationThe activity or item held up, and where4th floor slab · Tower B
Date of occurrenceThe day the hindrance started12 Sep 2026
Date of removalThe day it was cleared18 Sep 2026
Period (days)Worked out: date of removal minus date of occurrence, plus one7
Overlapping period (days)Days already counted under another hindrance0
Net delay (days)Worked out: period minus overlapping period7
Hours lostFor hindrances shorter than a day3 (late cement delivery)
Reported by and remarksWho recorded it, and the letter or email that backs it upLetter ref. GMD/TB/112
03

Overlapping hindrances: don't count the same day twice

Hindrances often run at the same time. In the example, the slab drawing was pending from 12 to 18 September, and heavy rain stopped work on 16 and 17 September. Work was held up for 7 days, not 9 - so the rain entry gets an overlapping period of 2 days and a net delay of 0.

Whoever checks an extension of time claim looks for exactly this. A register that counts overlapping hindrances twice overstates the delay and loses credibility; one that separates them gives a net figure that holds up.

04

Tips for a register that holds up in a claim

  1. 1Enter each hindrance on the day it starts - a register written months later from memory is easy to challenge.
  2. 2Write to the client or engineer-in-charge when a hindrance starts, and note the letter or email reference in Remarks.
  3. 3Fill in the date of removal as soon as it's cleared, so the period is exact.
  4. 4Keep photos of the site on hindrance days.
  5. 5Get the register signed by the engineer-in-charge regularly - for example every month - not only at the end of the project.
05

Or record hindrances as part of the daily report

A separate register is one more job, and it's the one that gets skipped. In Raidzo, site engineers note hindrances in the daily progress report - cause, details and hours lost - and the hindrance register collects them by itself, grouped by cause, for any date range, ready to export to CSV or PDF. Free for up to 10 users.

Raidzo's register counts hours lost and uses the same causes as this format. It doesn't work out periods, overlapping days or net delay in days - if your contract asks for those, export the hindrances from Raidzo and add them to this Excel register.

FAQ

Frequently asked questions

What is the format of a hindrance register?

A numbered table with the nature of each hindrance, its details, the work affected, the dates of occurrence and removal, the period, any overlapping period, the net delay, who reported it and remarks - signed by the contractor and the engineer-in-charge.

What is the overlapping period in a hindrance register?

Days that are already counted under another hindrance. They're subtracted from the period, so the same day isn't claimed twice when the net delay is worked out.

Who maintains the hindrance register?

Usually the contractor's site engineer records it, and the client's engineer-in-charge checks and signs it. On many contracts it's the main record looked at when deciding an extension of time.

How do I record a hindrance that lasted only a few hours?

Put the same date in both date columns and enter the time lost in Hours lost. The register then leaves it out of the day count, so a late delivery isn't counted as a full day.

Is this hindrance register format free?

Yes. Download the Excel file without signing up. It also opens in Google Sheets, WPS Office and LibreOffice.

Try it on your next project

Set up your organization in a couple of minutes. Free for up to 10 users, with every feature included.

Create your workspace

Prefer a walkthrough? We'll show you Raidzo on a 20-minute call. See pricing